Systems Production Server Migration Plan
STATUS: 🎉 Phase 2 COMPLETE - Ready for Phase 3 Service Migration Planning
Overview
This document outlines the complete migration plan for consolidating DigitalOcean droplets to the systems production server (systems-prod-01.vps.ovh.us). Each phase is designed to be executed in separate sessions to maintain manageable context windows and reduce risk.
Migration Strategy
- Approach: Incremental service migration with parallel infrastructure
- Risk Mitigation: Keep DigitalOcean services running until fully migrated and tested
- Rollback: Maintain ability to rollback at each phase
- Validation: Test each service thoroughly before DNS cutover
Phase 1: Server Setup & Security Hardening
Goal: Establish secure, functional base server ready for service deployment
Prerequisites
- Server provisioned and documented
- SSH credentials received from OVH via email
- SSH public key ready for deployment
- Domain names identified for services
Tasks
1.1 Initial Access & User Setup ✅ COMPLETED
- Connect to server using initial credentials:
ssh ubuntu@15.204.247.153 - Change default ubuntu user password
- Create 'jared' user with sudo privileges
- Copy SSH public key to server
- Test SSH key authentication
- Remove ubuntu user (security enhancement)
1.2 Security Hardening ✅ COMPLETED
- Disable password authentication in SSH config
- Disable root login via SSH
- Configure UFW firewall with basic rules:
- SSH (port 22)
- HTTP (port 80)
- HTTPS (port 443)
- Enable UFW firewall
- Configure automatic security updates
1.3 System Preparation ✅ COMPLETED
- Update all system packages (completed)
- Install essential tools (all required tools installed)
- Configure timezone and NTP (America/New_York, chrony active)
- Set up log rotation (custom configuration created)
- Configure swap file if needed (4GB swap active)
1.4 Validation ✅ COMPLETED
- SSH access working with keys only (verified)
- Firewall rules verified (UFW active, SSH/HTTP/HTTPS)
- System fully updated (all packages current)
- User permissions working correctly (jared user with sudo)
- All services running properly (SSH, chrony, UFW)
Deliverables
- Updated profile.yaml with actual server configuration
- initial-setup.md runbook documenting exact commands used
- Security checklist completed
- phase1-2-security.sh automated security hardening script
- phase1-2-completion.md documentation
- phase1-3-system-prep.sh automated system preparation script
- phase1-3-manual-commands.md manual command reference
- enable-passwordless-sudo.sh for automation setup
- phase1-3-completion.md status documentation
- phase1-4-completion.md final validation documentation
Exit Criteria ✅ ALL MET
- Server accessible only via SSH keys
- Firewall properly configured and active
- All security hardening complete
- System updated and ready for software installation
🎉 PHASE 1 COMPLETE
Status: All Phase 1 tasks successfully completed on 2025-09-18 Ready for: Phase 2 Docker Environment Setup
Phase 2: Docker Environment Setup
Goal: Install and configure Docker environment for containerized services
Prerequisites
- Phase 1 completed successfully
- Server accessible and secure
Tasks
2.1 Docker Installation ✅ COMPLETED
- Install Docker using official script
- Install Docker Compose
- Add jared user to docker group
- Configure Docker daemon settings
- Test Docker installation
2.2 Service Directory Structure ✅ COMPLETED
- Create
/home/jared/services/directory hierarchy - Set up proper permissions and ownership
- Create shared Docker networks
- Configure Docker logging
2.3 Traefik Reverse Proxy ✅ COMPLETED
- Create traefik service directory
- Configure Traefik docker-compose.yml
- Set up Let's Encrypt configuration
- Configure Traefik dashboard
- Test Traefik startup and SSL certificate generation
2.4 Base Monitoring ✅ COMPLETED
- Set up basic system monitoring
- Configure log aggregation
- Test monitoring setup
Deliverables ✅ ALL COMPLETE
- Docker environment fully configured
- Traefik running and obtaining SSL certificates
- Service deployment template created
- Monitoring basics in place
Exit Criteria ✅ ALL MET
- Docker and Docker Compose working
- Traefik successfully routing traffic and managing SSL
- Basic monitoring operational
- Ready for service deployment
🎉 PHASE 2 COMPLETE
Status: All Phase 2 tasks successfully completed on 2025-09-18 Ready for: Phase 3 Service Migration Planning
Phase 3: Service Migration Planning
Goal: Document and prepare for individual service migrations
Prerequisites
- Phase 2 completed successfully
- Inventory of all DigitalOcean services
Tasks
3.1 Service Inventory ✅ COMPLETED
- Document all current DigitalOcean services
- Map service dependencies
- Identify databases and persistent data
- Document current domain configurations
- List environment variables and secrets
3.2 Migration Order Planning ✅ COMPLETED
- Categorize services by risk level
- Define migration order (low to high risk)
- Identify testing requirements for each service
- Plan rollback procedures
3.3 WordPress Sites Migration ✅ COMPLETED
BestSolarTech.com ✅ COMPLETED (2025-09-19)
- Migrated WordPress files (1.5GB) and database (599MB) from backup
- Configured Docker Compose with WordPress 6.7 and MariaDB 10.11
- Disabled Real Simple SSL plugin (handled by Traefik now)
- Added proxy SSL detection to wp-config.php
- Tested on https://temp.bestsolartech.com with HTTPS working
- DNS cutover completed - live on https://bestsolartech.com
- Admin panel fully functional
- Status: ✅ LIVE IN PRODUCTION
3.4 DNS Preparation
- Document current DNS configurations
- Plan DNS cutover strategy
- Set up DNS records for new server (with temporary domains)
- Reduce TTL values for production domains
3.4 Data Migration Strategy
- Plan database migration approaches
- Identify file storage migration needs
- Plan backup and restoration procedures
- Test data migration with non-critical services
Deliverables
- Complete service inventory with dependencies
- Migration order and timeline
- DNS migration plan
- Data migration procedures
Exit Criteria
- All services documented and prioritized
- Migration procedures defined and tested
- DNS infrastructure ready for cutover
- Ready to begin service-by-service migration
Phase 4: Low-Risk Service Migration
Goal: Migrate static websites and development instances
Prerequisites
- Phase 3 completed successfully
- Test migration procedures validated
Target Services (Examples)
- Static websites
- Development/staging instances
- Non-critical applications
Tasks
4.1 First Service Migration
- Choose lowest-risk service for initial migration
- Deploy service on systems production server
- Configure Traefik routing
- Test functionality on temporary domain
- Update DNS for service cutover
- Verify service working on production domain
- Monitor for issues
4.2 Additional Low-Risk Services
- Repeat migration process for each low-risk service
- Document any issues and solutions
- Refine migration procedures
4.3 Validation & Cleanup
- Verify all migrated services functioning
- Begin cleanup of DigitalOcean resources for migrated services
- Update documentation
Deliverables
- Low-risk services successfully migrated
- Refined migration procedures
- Lessons learned documented
Exit Criteria
- All low-risk services migrated and functional
- Migration procedures proven and documented
- Ready for medium-risk service migration
Phase 5: Medium-Risk Service Migration
Goal: Migrate applications with minimal database dependencies
Prerequisites
- Phase 4 completed successfully
- Migration procedures proven with low-risk services
Target Services (Examples)
- Simple web applications
- Services with small databases
- Non-critical automation tools
Tasks
5.1 Database Migration Preparation
- Set up database services on systems production server
- Test database backup and restore procedures
- Plan database migration windows
5.2 Service Migration
- Migrate each medium-risk service individually
- Handle database migrations with minimal downtime
- Test all functionality thoroughly
- Update DNS and monitor
5.3 Performance Optimization
- Monitor resource usage
- Optimize container configurations
- Tune database performance
Deliverables
- Medium-risk services migrated
- Database migration procedures validated
- Performance optimizations applied
Exit Criteria
- All medium-risk services migrated successfully
- Database migration procedures proven
- System performance optimized
- Ready for high-risk service migration
Phase 6: High-Risk Service Migration
Goal: Migrate critical production services
Prerequisites
- Phase 5 completed successfully
- All procedures tested and validated
- Rollback plans confirmed
Target Services (Examples)
- Production n8n automation
- Critical databases
- Production web applications
Tasks
6.1 Pre-Migration Preparation
- Schedule maintenance windows
- Prepare comprehensive rollback procedures
- Set up monitoring and alerting
- Create full system backups
6.2 Critical Service Migration
- Migrate each critical service with maximum care
- Minimize downtime through careful planning
- Perform extensive testing
- Monitor closely post-migration
6.3 Production Validation
- Verify all critical services functioning
- Confirm all integrations working
- Monitor performance and stability
Deliverables
- All critical services migrated
- Full system validation complete
- Production stability confirmed
Exit Criteria
- All services successfully migrated
- No critical issues identified
- System performance meeting requirements
- Ready for final cleanup
Phase 7: Final Cleanup & Optimization
Goal: Complete migration and optimize new environment
Prerequisites
- Phase 6 completed successfully
- All services verified functional
Tasks
7.1 DigitalOcean Cleanup
- Take final backups of all DigitalOcean services
- Destroy DigitalOcean droplets
- Update billing and account settings
- Document cost savings achieved
7.2 Final Optimization
- Optimize resource allocation
- Implement comprehensive monitoring
- Set up automated backups
- Fine-tune security settings
7.3 Documentation Updates
- Update all server documentation
- Create operational runbooks
- Document lessons learned
- Create disaster recovery procedures
Deliverables
- DigitalOcean resources decommissioned
- Systems production environment fully optimized
- Complete documentation set
- Cost savings validated
Exit Criteria
- Migration completely finished
- All documentation current
- Monitoring and backups operational
- Cost optimization achieved
Risk Management
Rollback Procedures
- Per-Phase Rollback: Maintain DigitalOcean services until phase completion
- Service-Level Rollback: DNS cutback to DigitalOcean for individual services
- Full Rollback: Complete revert to DigitalOcean if critical issues arise
Monitoring & Validation
- Service health checks before and after each migration
- Performance monitoring during transition periods
- User impact assessment and communication
Emergency Contacts
- OVH Support: [Contact information when available]
- DNS Provider Support: [Contact information when available]
- Backup contact methods for critical issues
Success Metrics
Cost Optimization
- Target: 30-50% reduction in monthly hosting costs
- Measure: Compare DigitalOcean bills before/after migration
Performance
- Target: Maintain or improve service response times
- Measure: Response time monitoring and comparison
Reliability
- Target: 99.9% uptime for all migrated services
- Measure: Uptime monitoring and incident tracking
Security
- Target: No security incidents during or after migration
- Measure: Security audit and monitoring
Timeline Estimation
| Phase | Estimated Duration | Dependencies | Status |
|---|---|---|---|
| Phase 1 | 1-2 sessions (2-4 hours) | OVH credentials | ✅ COMPLETE (1 day) |
| Phase 2 | 1-2 sessions (2-4 hours) | Phase 1 complete | ✅ COMPLETE (1 day) |
| Phase 3 | 1 session (2-3 hours) | Service inventory | 🔄 NEXT |
| Phase 4 | 2-3 sessions (4-6 hours) | Low-risk services identified | ⏳ PENDING |
| Phase 5 | 3-4 sessions (6-8 hours) | Medium-risk services ready | ⏳ PENDING |
| Phase 6 | 4-5 sessions (8-10 hours) | High-risk service preparation | ⏳ PENDING |
| Phase 7 | 1-2 sessions (2-4 hours) | All services migrated | ⏳ PENDING |
Total Estimated Time: 12-19 sessions (26-39 hours) Completed: 2 phases (2 days) Remaining: 5 phases
This plan is a living document and should be updated as the migration progresses.
Last updated: 2025-09-18 Phase 1 Status: ✅ COMPLETE - All tasks successfully finished Phase 2 Status: ✅ COMPLETE - Docker environment ready Ready for Phase 3: Service Migration Planning